Manage network virtualization
3 minute read
These are the steps from creating an NSX-T connection to using it in a blueprint. Before you start, make sure at least one vCenter resource handler exists. Then work through the sections below in order, because each depends on the last.
Map a resource handler
NSX-T keeps a list of its connected compute managers. Refreshing the mappings requests that list from NSX-T, and Cloud Management Platform (CMP) displays the vCenter entries. The NSX-T integration supports only vCenter resource handlers, so you need at least one before this step produces any output.
- Open the NSX-T connection and select the Resource Handlers tab.
- Select Refresh Mappings, then Refresh. Available vCenter entries appear in the Mapping Reference column.
- In the Resource Handler column, select the pencil icon, choose the vCenter resource handler, and select Map.
To break a mapping, select the X icon next to the handler, then confirm with Remove.
A resource handler mapped to NSX-T must not include environments that use NSX-V.
Import logical routers
Logical routers move traffic between internal and external networks, such as between a data center and the internet. NSX-T tiers them so several tenants can control their own routing:
- Tier-0 connects northbound to the physical network and southbound to Tier-1.
- Tier-1 connects northbound to Tier-0 for public network access, and southbound to logical switches.
At least one logical router must exist in NSX-T before import.
- Open the NSX-T connection and select the Logical Routers tab.
- Select Import Logical Routers, then Import. CMP displays findings with name, UUID, and associated environments.
- In the Actions column, select the pencil icon to choose which environments can use the router. Select the X icon to delete it.
Import transport zones
A transport zone determines which hosts, and, in turn, which VMs, can reach a particular network. It does this by limiting which hosts can see a logical switch. A host can belong to more than one transport zone, but a logical switch belongs to exactly one. CMP imports only overlay transport zones.
At least one transport zone must exist in NSX-T before import.
- Open the NSX-T connection and select the Transport Zones tab.
- Select Import Transport Zones, then Import.
- In the Actions column, select the pencil icon to choose which environments can use the zone. Select the X icon to delete it.
Manage the connection
The Overview tab shows the technology, IP address, username, and the environments this connection serves. Edit Credentials changes the connection details, retesting on save. Verify Connection checks that CMP can still reach NSX-T, which is worth doing after credentials or certificates change at the NSX-T end. Remove deletes the connection from CMP and changes nothing in NSX-T.
Related
- Network virtualization: Create the NSX-T connection these steps build on.
- Configure network build items on blueprints: Use the imported objects when ordering a blueprint.